Demolition on DC's Southeast Freeway to Limit Travel


closure
Part of the Southeast Freeway in D.C. will be off limits this weekend. Click to enlarge. (Photo courtesy of DDOT)


www.AnacostiaRiverRealty.com


Thursday, January 7, 2010

New DC 5 cent Bag Tax To Clean the Anacostia River Begins


By BETH PARKER/myfoxdc


D.C. residents are getting creative about how they transport their groceries. The D.C. bag fee took effect January 1.

Bring your own reusable bags to a store and you'll pay no additional fees. But paper and plastic bags will cost a customer five cents each. Some of the money goes to the retailer. Most will be spent cleaning up the Anacostia River.

It doesn't just apply to grocery stores. It's any business that sells food or alcohol.

The D.C. bag law can be complicated, especially when it comes to restaurants. Here's how it works. If a restaurant has what is called a "deli license" and has no seating, customers must pay whether they leave with a paper or plastic bag. But if you leave a sit-down restaurant with take-out or a doggie bag and it's in a paper bag, you're exempt. You don't have to pay the extra five cents. If you leave with a plastic bag, you have to pay.

D.C. says there is a bottom line. Bring your bags.

Maryland Delegate Al Carr and Virginia Delegate Adam Ebbin now say they will soon introduce bills that mirror the D.C. law.




ANACOSTIA RIVER REALTY: The east of the Anacostia River experts. http://www.anacostiariverrealty.com/

Thursday, December 24, 2009

11th Street Bridge Project Construction to Begin

On or about Tuesday, Dec. 29, contractors will begin 11th Street Bridge Project construction activities,

which may be noticeable to area residents and businesses but ultimately result in a number of important

benefits.

Initial work will include pile driving in the Anacostia River to construct foundations for three new bridges –

one for local and two for freeway traffic. Barrier placement, off-roadway clearing and drainage work also is

to begin adjacent to both directions of DC 295, later resulting in shoulder encroachments and minor lane

shifts. Eventually, land-side pile driving on both sides of the river will be required to construct new

connecting ramps and improve the highway. To minimize impacts, noise and vibration levels will be

monitored at all times.

The new bridges will be constructed between the existing bridges, which are projected to serve almost

180,000 vehicles per day by 2030, allowing contractors to maintain all existing travel movements and 12-

foot travel lanes except during approved work in off-peak travel hours.

In addition, contractors will practice good neighbor construction by establishing designated haul routes,

having most materials delivered via the river or highway, controlling dust, and requiring that workers not

park on neighborhood streets.

Scheduled for completion in mid-2013, the $300 million project will:

· Improve mobility by providing separate freeway and local traffic connections to both directions of

DC 295, the Southeast-Southwest Expressway and local streets on both sides of the Anacostia River.

· Provide a shared path for pedestrians and bicycles, as well as rails to allow future streetcar

connections

· Replace the existing functionally deficient and structurally obsolete bridges

· Provide an additional alternate evacuation route from our Nation’s capital, and

· Include new trail connections, improved drainage and other environmental investments

The 11th Street Bridge Project and District Department of Transportation regret any inconvenience and appreciate your understanding during construction.

For more information, please call Public Information Manager Bryon Johnston at 202-484-2330 ext 137 or email ddotpublicaffairs@dc.gov.


ANACOSTIA RIVER REALTY: The East of the River Experts.